Lights & Sirens

Go behind the yellow tape with The News Tribune

NOTICE: Lights & Sirens has moved.

With the launch of our new website, we've moved Lights & Sirens.
Visit the new section.

Repairs at South 15th and Market streets will take at least until the end of April

Post by Kris Sherman / The News Tribune on March 25, 2011 at 4:58 pm with 1 Comment »
March 25, 2011 4:58 pm

The hole in the road at South 15th and Market streets  in Tacoma is going to stay there longer than originally thought – keeping the street closed and forcing detours, the city said his afternoon.

The work likely won’t be done until the end of April.

Traffic can still get to businesses but there are diversions around the work.

Crews have been working on repairs for more than a week after a sewer line built in 1906 collapsed.

They first thought repairs would take several days. As recently as Tuesday, an assiatant public works director told City Council members it should be wrapped up by April 8.

But the deepeer workers dig into the project, the more they realize needs to be done, the city said this afternoon in a news release.

“As we continue to excavate, the scope continues to increase due to the existing condition of the pipe,” Public Works construction division manager Rae Bailey said.

“In fact, today we discovered that we will have to replace additional storm and sanitary sewer pipe along South 15th up to the alley between Market and Fawcett because it is cracked,” he added.

Tucci and Sons is doing the repair work under an emergency $200,000 contract.

Here’s a copy of the news release:

Excavation reveals need for further sewer repairs near South 15th & Market
Traffic diversions will continue; access to businesses will be maintained

Traffic diversions near South 15th and Market streets in downtown Tacoma are expected to continue through the end of April. This exceeds initial estimates because excavation revealed the sewer lines in this area will require more extensive repair.

A sewer overflow on March 15 was caused by a collapsed sewer line in need of immediate repair to avoid public health and safety issues.

City crews established a bypass pumping system to divert flows around the collapsed sewer main line. A contractor began emergency repairs March 17.

“As we continue to excavate, the scope continues to increase due to the existing condition of the pipe,” said Rae Bailey, Public Works Construction Division manager.

“In fact, today we discovered that we will have to replace additional storm and sanitary sewer pipe along South 15th up to the alley between Market and Fawcett because it is cracked.”

Crews from Tucci and Sons, under emergency contract with the City of Tacoma to make the repair, are working 10-hour shifts Monday through Saturday. Work is expected to be completed by the end of April, depending on weather conditions.

“We are trying to minimize impacts to all businesses and traffic as we complete the repair,” said Bailey.

The primary work zone is between Court C and Court D on South 15th Street and on Market Street between South 13th and South 15th streets. Traffic diversions are in place. Access to the apartment complex and businesses in this area are being maintained.

The sewer in this area is clay pipe and more than 100 years old.

Leave a comment Comments → 1
  1. The engineering back then is pretty good. I hope that my knee holds
    up that well. The Roman aqueducts have you beat by a bit.

*
We welcome comments. Please keep them civil, short and to the point. ALL CAPS, spam, obscene, profane, abusive and off topic comments will be deleted. Repeat offenders will be blocked. Thanks for taking part and abiding by these simple rules.

Follow the comments on this post with RSS 2.0